Force Protection Building

Ladson, SC

 

To facilitate achieving the goals and needs of the armed forces, Force Protection needed more automation in their vehicle production line. Berenyi Inc. was choosen as structural designer and construction manager for the installation of the new automation line. Coordination between automotive, mechanical, electrical, and general contractor efforts was handled by Berenyi, Inc.

The project is summarized by a new 400 ft. long, 15 station automated assembly line built inside an existing plant. Normal operation continued during construction. New annex buildings constructed to support main assembly line where included in the design and construction scope.

 

 

Services Provided (click service below to browse projects)

Architectural Services Construction Management Construction Services Facility Upgrades Industrial Engineering Site Improvements Structural Engineering