• Existing damaged piers
  • Existing damaged piers
  • Removing loose and damaged concrete
  • Cleaning loose concrete from existing piers
  • Jacketed/Grouted pier
  • Completed piers

ArcelorMittal - Castor Foundation Improvement

Georgetown, SC

 

During the 2012 winter shutdown ArcelorMital asked Berenyi to improve the foundation under the castor table. The work included removing failed concrete, installation of additional reinforcement, design / fabrication / and installation of new steel jackets around foundation piers, and new non-shrink grout reinforcement. The project was a completed on schedule and judged a complete success.

Thanks ArcelorMittal for allowing us to be involved! 

Services Provided (click service below to browse projects)

Civil & Structural Maintenance Construction Management Construction Services Facility Upgrades Foundation Construction Heavy Structural Steel Industrial Engineering Marine Construction Plant Maintenance Plant Shut Down Structural Design Turn Key Projects

Other ArcelorMittal Projects